Order of Work

Coordinating Plumbing and Electrical Rough-Ins

Marcus Tremblay  / 

Your basement framing is complete. The rooms are defined, but they are just skeletons of studs. Now you hit one of the most crowded phases of the project: the rough-ins. This is when your plumber, electrician, and HVAC technician install the guts of your new living space inside the walls and ceiling. Get the sequence wrong and you waste time and money. If you are acting as your own general contractor, this is on you. If you hired one, this is where they earn their fee.

What is a Rough-In?

A rough-in is the installation of all the background parts of a system. It is everything that will be hidden behind insulation, vapour barrier, and drywall. For plumbing, this means running all the water supply lines to your future sinks, showers, and toilets. More important, it means running all the drain and vent pipes. The drainpipes have to be installed with a specific slope so gravity can do its work. The vent pipes have to run up through the house and terminate correctly so the drains function properly.

For electrical, the rough-in means installing all the device boxes for switches, outlets, and light fixtures. It includes running all the electrical cables from the panel location to these boxes. The wires are left inside the boxes, ready for the finish stage, but no devices like switches or receptacles are installed yet. The same principle applies to your gasfitter and your HVAC technician. All pipes, ducts, and lines go in now.

The Proper Sequence: Plumbing, HVAC, Electrical

There is a correct order for this work. It is based on practicality and the physical constraints of the materials. The trade with the biggest, least flexible components goes first.

Plumbing is almost always first. Drainpipes are large, rigid, and absolutely dependent on slope. A plumber cannot just route a three inch ABS drainpipe anywhere. It has to follow a specific downward path from the fixture to the main stack. This gives plumbing top priority for routing through the floor joists and wall cavities.

HVAC ducting is next, or sometimes happens at the same time. The supply and return air ducts are also large and inflexible. Your HVAC tech needs to find clear paths for these big rectangular or round ducts. They work around the plumbing that is already in place.

Electrical comes last. Electrical wire is flexible. An electrician can drill smaller holes and snake wires around pipes and ducts that are already installed. It is far simpler to route a wire around a drainpipe than it is to re-route a drainpipe because an electrical wire is in the way. This order minimizes conflict and rework.

The Inspection Bottleneck

You cannot cover any of this work until it has been inspected and passed by the City of Calgary. Each of these trades requires a separate permit, pulled by the certified tradesperson doing the work. The building permit for the overall development is separate from the trade permits for plumbing, electrical, and gas.

The sequence for inspection is straightforward:

  1. All rough-ins must be 100 percent complete. That means every pipe, wire, duct, and box is secured in place.
  2. The tradespeople or your general contractor request their specific inspections from the City.
  3. A City Safety Codes Officer for each discipline visits the site. They have the approved drawings and verify that the installation matches the plans and meets all requirements of the Alberta Building Code. They check things like the slope of drains, the type of wire used, and the supports for gas lines.
  4. If the work passes, the inspector leaves a green sticker. If it fails, they leave a report detailing the deficiencies that must be corrected.

You cannot proceed to insulation and drywall until you have passed all of these rough-in inspections. Covering up work that has not been approved is a serious mistake that will result in a tear-out order. For specifics on the city's process, you should always consult the official City of Calgary permit questions page for the current rules.

Conflicts in the Walls and Ceilings

Even with the right sequence, trades can get in each other's way. The most common conflict area is drilling holes through floor joists. The code has strict rules about the size and location of holes and notches in structural members to prevent weakening your house's floor system. A plumber needing a large hole for a drainpipe and an electrician needing a path for multiple cables might both target the same joist bay.

A good set of drawings is your first line of defense. Planning where large items like a shower drain or a main HVAC trunk line will run can prevent most of the surprises. The second line of defense is communication on site.

Without a plan, the first person on site wins, which can create problems for the next trade. This is where a project coordinator or an experienced general contractor earns their money. They walk the site with the tradespeople before they start drilling and make sure everyone's needs can be met without compromising the structure.

Questions for Your General Contractor

If you are hiring a contractor to manage your project, you need to be confident they can handle this stage. Do not be shy about asking direct questions about their process.

  • How do you schedule your plumbing, HVAC, and electrical trades for the rough-in phase?
  • Who is on site to coordinate the trades and resolve conflicts over routing?
  • What is your procedure if a conflict arises between trades, for example, over drilling joists?
  • How do you manage and track the different trade permits and their inspections?
  • Do you have a policy of waiting for all passed inspection reports before scheduling insulation delivery?

Their answers will tell you a lot about their experience level. A pro will have clear, immediate answers. A less experienced person might hesitate. This phase of the project is about process and sequence. Getting it right protects the value of your project and prevents some of the worst kinds of delays. The work gets buried in the walls, but if it is not done right, it will show itself later.

Marcus Tremblay coordinated renovation projects in Calgary. The Basement Brief is his own writing and is not affiliated with any contractor.

All briefs

The Basement Brief is written by Marcus Tremblay in Calgary. Independent. No advertising, no sponsored posts, no affiliate links.

About / Contact

Codes and permit requirements change. Confirm anything you plan to act on with the City of Calgary or the Alberta Safety Codes Council.